- Question #101Risk Monitoring and Reporting
Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to r...
Earned Value ManagementSchedule VarianceProject Performance Measurement - Question #102Risk Strategy and Planning
You are the project manager of the NHQ project for your company. You are working with your project team to complete a risk audit. A recent issue that your project team responded to...
Risk Response StrategiesAvoidanceSchedule ManagementThreat Response - Question #103Risk Strategy and Planning
Gary is the project manager for his organization. He is working with the project stakeholders on the project requirements and how risks may affect their project. One of the stakeho...
Project Risk DefinitionUncertaintyProject Objectives - Question #104Perform Targeted Risk Analysis
You work as a project manager for BlueWell Inc. Management has asked you to work with the key project stakeholder to analyze the risk events you have identified in the project. The...
Qualitative Risk AnalysisRisk PrioritizationStakeholder EngagementProject Performance Improvement - Question #105Risk Strategy and Planning
A high-profile, high-priority project within your organization is being created. Management wants you to pay special attention to the project risks and do all that you can to ensur...
Utility functionRisk aversionOrganizational risk toleranceRisk appetite - Question #106Risk Process Facilitation
You are the project manager of the BJA Project for your company. Management is worried about one of the identified risks in your project. The risk event has a probability of 90 per...
Risk Response StrategiesMitigationThreat Management - Question #107Risk Strategy and Planning
Ben is the project manager of the YHT Project for his company. Alice, one of his team members, is confused about when project risks will happen in the project. Which one of the fol...
Risk definitionNature of riskFuture uncertaintyRisk vs. Issue - Question #108Risk Strategy and Planning
There are seven risk responses, a project manager can use to address risk events. Which one of the following is a risk response that is appropriate for positive or negative risk ev...
Risk response strategiesAcceptance risk responseThreat responsesOpportunity responses - Question #109Risk Monitoring and Reporting
You are the project manager of the NHQ Project for your company. You are discussing some of the project issues that need to be resolved in the project. You and the project stakehol...
Issue managementIssue logDocumentationRisk resolution - Question #110Perform Targeted Risk Analysis
You are the project manager of the GHY project. In your organization you must follow certain enterprise environmental factors that establish the rules for risk management . One of...
Qualitative Risk AnalysisRisk Analysis TechniquesEnterprise Environmental FactorsRisk Monitoring - Question #111Risk Strategy and Planning
You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response p...
Risk response planningPMBOK outputsProject Risk ManagementRisk management processes - Question #112Stakeholder Engagement
A project manager must have certain interpersonal skills to communicate with stakeholders and manage their expectations of the project work. Which of the following interpersonal sk...
Interpersonal skillsCommunicationStakeholder managementProject success factors - Question #113Risk Strategy and Planning
You are the project manager of the GHG project for your company. You have identified the project risks, completed qualitative and quantitative analysis, and created risk responses....
Risk Management PlanRisk AuditsRisk MonitoringPlanning - Question #114Risk Strategy and Planning
You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're your company. You have completed the risk analysis processes for the risk events. You and th...
Risk response planningRisk transferenceThreat responseRisk management strategies - Question #115Risk Strategy and Planning
Which types of project tends to have more well-understood risks?
Project typesRisk characteristicsRecurrent projectsRisk understanding - Question #116Perform Targeted Risk Analysis
You are the project manager of a large construction project. You are evaluating the strengths, weaknesses, opportunities, and threats involved in a project. In which of the followi...
SWOT AnalysisIdentify RisksRisk IdentificationRisk Management Process - Question #117Risk Monitoring and Reporting
You are the project manager of the NHQ project for your company. Management has told you that you must implement an agreed upon contingency response if the Cost Performance Index i...
Earned Value ManagementCost Performance IndexRisk MonitoringRisk Response Triggers - Question #118Risk Strategy and Planning
Harry works as a project manager for BlueWell Inc. He is determining how to conduct the risk management activities for a project. According to the PMBOK, there are six inputs to th...
Plan Risk ManagementProcess InputsPMBOK GuideRisk Planning - Question #119Perform Targeted Risk Analysis
Which of the following are parts of SWOT Analysis? Each correct answer represents a complete solution. Choose all that apply.
SWOT AnalysisRisk Identification TechniquesQualitative Risk Analysis - Question #120Risk Monitoring and Reporting
Adrian is a project manager for a new project using a technology that has recently been released and there's relatively little information about the technology. Initial testing of...
Risk RegisterRisk DocumentationRisk TrackingMonitor Risks - Question #121Perform Targeted Risk Analysis
Sensitivity analysis is a technique for systematically changing parameters in a model to determine the effects of such changes and is useful for computer modelers for a range of pu...
Sensitivity AnalysisQuantitative Risk AnalysisDecision SupportRisk Modeling - Question #122Risk Strategy and Planning
Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a sizeable discount on all hardware if his order total for the project is...
Positive Risk ResponseOpportunity ManagementSharing StrategyRisk Response Planning - Question #123Stakeholder Engagement
Della works as a project manager for Tech Perfect Inc. She is studying the documentation of planning of a project. The documentation states that there are twenty-eight stakeholders...
Communication ChannelsStakeholder ManagementProject CommunicationsFormula Application - Question #124Perform Targeted Risk Analysis
You are the project manager for your organization. You are working with your project team to complete the qualitative risk analysis process. The first tool and technique you are us...
Qualitative Risk AnalysisProbability and ImpactRisk Assessment - Question #125Perform Targeted Risk Analysis
You are the project manager of the GHG project. You are preparing for the quantitative risk analysis process. You are using organizational process assets to help you complete the q...
Organizational Process AssetsQuantitative Risk AnalysisRisk InputsHistorical Information - Question #126Risk Strategy and Planning
Which of the following processes looks at the complex web of actors, rules, conventions, processes, and mechanisms concerned with how relevant risk information is collected, analyz...
Risk GovernanceRisk Management FrameworkOrganizational RiskDecision Making - Question #127Risk Monitoring and Reporting
You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project ha...
Cost Performance Index (CPI)Earned Value Management (EVM)Performance MeasurementRisk Triggers - Question #128Perform Targeted Risk Analysis
You work as a project manager for BlueWell Inc. You are performing the quantitative risk analysis for your project. One of the project risks has a 50 percent probability of happeni...
Expected Monetary ValueQuantitative Risk AnalysisRisk ProbabilityRisk Impact - Question #129Perform Targeted Risk Analysis
Joyce is the project manager for her company. Joyce and her project team are working through the quantitative analysis for certain risk events within her project. According to the...
Sensitivity AnalysisQuantitative Risk AnalysisRisk Analysis Techniques - Question #130Risk Strategy and Planning
You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative...
Risk response planningNegative risk responsesThreat strategies - Question #131Risk Strategy and Planning
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation...
Risk IdentificationProcess InputsPMBOK ProcessesProject Management Plan - Question #132Risk Strategy and Planning
Where can a project manager find risk-rating rules?
Organizational Process AssetsRisk rating rulesRisk assessmentInputs to risk management - Question #133Risk Monitoring and Reporting
As a part of monitoring and controlling the project, the project manager should update the risk register. The project manager should update the risk register with information on ri...
Risk RegisterMonitor RisksRisk Response OutcomesRisk Event Outcomes - Question #134Perform Targeted Risk Analysis
You are the project manager of the CUL project in your organization. You and the project team are assessing the risk events and creating a probability and impact matrix for the ide...
Qualitative Risk AnalysisData QualityRisk Data RequirementsCredibility - Question #135Perform Targeted Risk Analysis
You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the proj...
Risk RegisterRisk Response PlanningMitigationProject Documents - Question #136Risk Monitoring and Reporting
You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declin...
Change ManagementChange Request LogProject DocumentationDecision Documentation - Question #137Perform Targeted Risk Analysis
You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only ou...
Quantitative risk analysisProcess outputsRisk registerRisk management - Question #138Perform Targeted Risk Analysis
Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update t...
Qualitative Risk AnalysisRisk Register UpdatesQuantitative Risk AnalysisRisk Management Process - Question #139Risk Strategy and Planning
The risk transference is referred to the transfer of risks to a third party, usually for a fee, it creates a contractual-relationship for the third party to manage the risk on beha...
Risk transferenceRisk response strategiesRisk response planning - Question #140Risk Strategy and Planning
David is the project manager of the NKL Project for his organization. He has been asked to create a proposal for a construction project for a client. David realizes that there are...
Risk response strategiesSharing riskPartnershipsThreat management - Question #141Risk Monitoring and Reporting
Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team...
Risk reassessmentRisk monitoringContinuous risk managementProject best practices - Question #142Risk Strategy and Planning
Which of the following risk responses delineates that the project plan will not be changed to deal with the risk?
Risk Response StrategiesRisk AcceptanceThreat Responses - Question #143Risk Monitoring and Reporting
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should...
Risk RegisterRisk ResponsesRisk DocumentationRisk Status - Question #144Perform Targeted Risk Analysis
You are the project manager of the NGH project for your organization. You want to create a causeand- effect diagram to help discover the root causes of the risks within the project...
Ishikawa diagramCause-and-effect diagramRoot cause analysisRisk analysis tools - Question #145Perform Targeted Risk Analysis
You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques...
Quantitative Risk AnalysisTools and TechniquesOrganizational Process Assets - Question #146Risk Process Facilitation
You are the project manager of RTF project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows causal factors...
Risk Identification TechniquesCause and Effect DiagramsRoot Cause AnalysisRisk Analysis Tools - Question #147Perform Targeted Risk Analysis
You are the project manager of the NNN project for your company. You and the project team are working together to plan the risk responses for the project. You feel that the team ha...
Quantitative risk analysisRisk management processesOverall project riskRisk response evaluation - Question #148Perform Targeted Risk Analysis
Sensitivity analysis is a technique for systematically changing parameters in a model to determine the effects of such changes and is useful for computer modelers for a range of pu...
Sensitivity AnalysisQuantitative Risk AnalysisRisk Analysis TechniquesDecision Making - Question #149Risk Monitoring and Reporting
You are the project manager of the NHH Project for your company and you have completed the risk analysis processes for the risk events. You and the project team have created risk r...
Risk response ownershipRisk response implementationAccountabilityRoles and responsibilities - Question #150Risk Monitoring and Reporting
You work as a project manager for BlueWell Inc. You have to communicate the causes of risk events to the stakeholders. Which risk diagramming technique you will use to communicate...
Risk communicationIshikawa diagramCause-and-effect analysisRisk reporting