nerdexam
PMIPMI

PMI-RMP · Question #102

PMI-RMP Question #102: Real Exam Question with Answer & Explanation

The correct answer is C: Avoidance. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You are the project manager of the NHQ project for your company. You are working with your project team to complete a risk audit. A recent issue that your project team responded to, and management approved, was to increase the project schedule because there was risk surrounding the installation time of a new material. Your logic was that with the expanded schedule there would be time to complete the installation without affecting downstream project activities. What type of risk response is being audited in this scenario?

Options

  • AParkinson's Law
  • BMitigation
  • CAvoidance
  • DLag Time

Topics

#Risk Response Strategies#Avoidance#Schedule Management#Threat Response

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions