PMIPMI
PMI-RMP · Question #102
PMI-RMP Question #102: Real Exam Question with Answer & Explanation
The correct answer is C: Avoidance. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You are the project manager of the NHQ project for your company. You are working with your project team to complete a risk audit. A recent issue that your project team responded to, and management approved, was to increase the project schedule because there was risk surrounding the installation time of a new material. Your logic was that with the expanded schedule there would be time to complete the installation without affecting downstream project activities. What type of risk response is being audited in this scenario?
Options
- AParkinson's Law
- BMitigation
- CAvoidance
- DLag Time
Topics
#Risk Response Strategies#Avoidance#Schedule Management#Threat Response
Community Discussion
No community discussion yet for this question.