nerdexam
PMI

PMI-RMP · Question #102

You are the project manager of the NHQ project for your company. You are working with your project team to complete a risk audit. A recent issue that your project team responded to, and management app

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #102. The question stem and answer options stay visible for context.

Risk Strategy and Planning

Question

You are the project manager of the NHQ project for your company. You are working with your project team to complete a risk audit. A recent issue that your project team responded to, and management approved, was to increase the project schedule because there was risk surrounding the installation time of a new material. Your logic was that with the expanded schedule there would be time to complete the installation without affecting downstream project activities. What type of risk response is being audited in this scenario?

Options

  • AParkinson's Law
  • BMitigation
  • CAvoidance
  • DLag Time

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Response Strategies#Avoidance#Schedule Management#Threat Response
Full PMI-RMP Practice