nerdexam
PMIPMI

PMI-RMP · Question #103

PMI-RMP Question #103: Real Exam Question with Answer & Explanation

The correct answer is C: It is an uncertain event that can affect at least one project objective.. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Gary is the project manager for his organization. He is working with the project stakeholders on the project requirements and how risks may affect their project. One of the stakeholders is confused about what constitutes risks in the project. Which of the following is the most accurate definition of a project risk?

Options

  • AIt is an uncertain event that can affect the project costs.
  • BIt is an uncertain event or condition within the project execution.
  • CIt is an uncertain event that can affect at least one project objective.
  • DIt is an unknown event that can affect the project scope.

Topics

#Project Risk Definition#Uncertainty#Project Objectives

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions