nerdexam
PMIPMI

PMI-RMP · Question #101

PMI-RMP Question #101: Real Exam Question with Answer & Explanation

The correct answer is D: -$269,000. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to reach this point of completion. What is the schedule variance for this project?

Options

  • A-$217,500
  • B20 percent
  • C-$174,000
  • D-$269,000

Topics

#Earned Value Management#Schedule Variance#Project Performance Measurement

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions