PMIPMI
PMI-RMP · Question #101
PMI-RMP Question #101: Real Exam Question with Answer & Explanation
The correct answer is D: -$269,000. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to reach this point of completion. What is the schedule variance for this project?
Options
- A-$217,500
- B20 percent
- C-$174,000
- D-$269,000
Topics
#Earned Value Management#Schedule Variance#Project Performance Measurement
Community Discussion
No community discussion yet for this question.