PMI
PMI-RMP · Question #101
Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to reach this point of c
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #101. The question stem and answer options stay visible for context.
Risk Monitoring and Reporting
Question
Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to reach this point of completion. What is the schedule variance for this project?
Options
- A-$217,500
- B20 percent
- C-$174,000
- D-$269,000
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Earned Value Management#Schedule Variance#Project Performance Measurement