PMI-RMP · Question #111
You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process…
The correct answer is B. Organizational process assets updates. According to the PMBOK Guide, the outputs of the Plan Risk Responses process are: (1) Risk register updates, (2) Risk-related contract decisions, (3) Project management plan updates, and (4) Project document updates. 'Organizational process assets updates' is NOT an output of…
Question
You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?
Options
- ARisk register updates
- BOrganizational process assets updates
- CProject document updates
- DRisk-related contract decisions
How the community answered
(51 responses)- A4% (2)
- B90% (46)
- C4% (2)
- D2% (1)
Explanation
According to the PMBOK Guide, the outputs of the Plan Risk Responses process are: (1) Risk register updates, (2) Risk-related contract decisions, (3) Project management plan updates, and (4) Project document updates. 'Organizational process assets updates' is NOT an output of Plan Risk Responses - it is an output of other processes such as Close Project or Phase and Manage Project Execution. Risk response planning focuses on defining strategies to address identified risks, and its outputs are limited to updates within the project's own documentation framework, not organizational-level assets.
Topics
Community Discussion
No community discussion yet for this question.