nerdexam
PMIPMI

PMI-RMP · Question #147

PMI-RMP Question #147: Real Exam Question with Answer & Explanation

The correct answer is B: Quantitative risk analysis. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You are the project manager of the NNN project for your company. You and the project team are working together to plan the risk responses for the project. You feel that the team has successfully completed the risk response planning and now you must initiate what risk process it is. Which of the following risk processes is repeated after the plan risk responses to determine if the overall project risk has been satisfactorily decreased?

Options

  • AQualitative risk analysis
  • BQuantitative risk analysis
  • CRisk identification
  • DRisk response implementation

Topics

#Quantitative risk analysis#Risk management processes#Overall project risk#Risk response evaluation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions