PMI-RMP · Question #147
You are the project manager of the NNN project for your company. You and the project team are working together to plan the risk responses for the project. You feel that the team has successfully…
The correct answer is B. Quantitative risk analysis. After risk response planning, quantitative risk analysis is repeated to numerically assess whether the planned responses have sufficiently reduced overall project risk to an acceptable level.
Question
You are the project manager of the NNN project for your company. You and the project team are working together to plan the risk responses for the project. You feel that the team has successfully completed the risk response planning and now you must initiate what risk process it is. Which of the following risk processes is repeated after the plan risk responses to determine if the overall project risk has been satisfactorily decreased?
Options
- AQualitative risk analysis
- BQuantitative risk analysis
- CRisk identification
- DRisk response implementation
How the community answered
(19 responses)- A5% (1)
- B89% (17)
- D5% (1)
Why each option
After risk response planning, quantitative risk analysis is repeated to numerically assess whether the planned responses have sufficiently reduced overall project risk to an acceptable level.
Qualitative risk analysis prioritizes risks by probability and impact ratings but does not quantify the degree of overall project risk reduction achieved through response planning.
Quantitative risk analysis is used iteratively - once after qualitative analysis to measure baseline project risk, and again after risk response planning to verify that the responses have adequately reduced the probability and impact of key risk events. This second pass provides a numerical confirmation that residual risk falls within the project's risk tolerance. The iterative nature of this process ensures responses are validated before implementation begins.
Risk identification is performed earlier in the process to discover risk events and is not repeated after response planning to verify whether overall project risk has decreased.
Risk response implementation (executing the responses) occurs after analysis confirms responses are adequate and is an execution activity, not an analytical process used to measure risk reduction.
Concept tested: Iterative quantitative risk analysis after response planning
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok