Perform Targeted Risk Analysis
Question
You are the project manager for your organization. You are working with your project team to complete the qualitative risk analysis process. The first tool and technique you are using requires that you assess the probability and what other characteristic of each identified risk in the project?
Options
- AImpact
- BRisk owner
- CCost
- DRisk category
Topics
#Qualitative Risk Analysis#Probability and Impact#Risk Assessment