PMIPMI
PMI-RMP · Question #123
PMI-RMP Question #123: Real Exam Question with Answer & Explanation
The correct answer is A: 378. See the full explanation below for the reasoning.
Stakeholder Engagement
Question
Della works as a project manager for Tech Perfect Inc. She is studying the documentation of planning of a project. The documentation states that there are twenty-eight stakeholders with the project. What will be the number of communication channels for the project?
Options
- A378
- B300
- C28
- D250
Topics
#Communication Channels#Stakeholder Management#Project Communications#Formula Application
Community Discussion
No community discussion yet for this question.