nerdexam
PMIPMI

PMI-RMP · Question #122

PMI-RMP Question #122: Real Exam Question with Answer & Explanation

The correct answer is A: Sharing. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a sizeable discount on all hardware if his order total for the project is more than $125,000. Right now, Eric is likely to spend $118,000 with vendor. If Eric spends $7,000 his cost savings for the project will be $12,500, but he cannot purchase hardware if he cannot implement the hardware immediately due to organizational policies. Eric consults with Amy and Allen, other project managers in the organization, and asks if she needs any hardware for their projects. Both Amy and Allen need hardware and they agree to purchase the hardware through Eric's relationship with the vendor. What positive risk response has happened in this instance?

Options

  • ASharing
  • BExploiting
  • CTransference
  • DEnhancing

Topics

#Positive Risk Response#Opportunity Management#Sharing Strategy#Risk Response Planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions