PMI-RMP · Question #125

PMI-RMP Question #125: Real Exam Question with Answer & Explanation

The correct answer is C: You will use organizational process assets to determine costs of all risks events within the current project.. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You are the project manager of the GHG project. You are preparing for the quantitative risk analysis process. You are using organizational process assets to help you complete the quantitative risk analysis process. Which one of the following is NOT a valid reason to utilize organizational process assets as a part of the quantitative risk analysis process?

Options

  • AYou will use organizational process assets for risk databases that may be available from industry sources.
  • BYou will use organizational process assets for studies of similar projects by risk specialists.
  • CYou will use organizational process assets to determine costs of all risks events within the current project.
  • DYou will use organizational process assets for information from prior similar projects.

Topics

#Organizational Process Assets#Quantitative Risk Analysis#Risk Inputs#Historical Information