nerdexam
PMIPMI

PMI-RMP · Question #141

PMI-RMP Question #141: Real Exam Question with Answer & Explanation

The correct answer is C: At every status meeting the project team project risk management is an agenda item.. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

Options

  • AProject risk management is scheduled for every month in the 18-month project.
  • BProject risk management has been concluded with the project planning.
  • CAt every status meeting the project team project risk management is an agenda item.
  • DProject risk management happens at every milestone.

Topics

#Risk reassessment#Risk monitoring#Continuous risk management#Project best practices

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions