nerdexam
PMIPMI

PMI-RMP · Question #142

PMI-RMP Question #142: Real Exam Question with Answer & Explanation

The correct answer is C: Acceptance. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Which of the following risk responses delineates that the project plan will not be changed to deal with the risk?

Options

  • AExploitation
  • BTransference
  • CAcceptance
  • DMitigation

Topics

#Risk Response Strategies#Risk Acceptance#Threat Responses

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions