PMIPMI
PMI-RMP · Question #142
PMI-RMP Question #142: Real Exam Question with Answer & Explanation
The correct answer is C: Acceptance. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Which of the following risk responses delineates that the project plan will not be changed to deal with the risk?
Options
- AExploitation
- BTransference
- CAcceptance
- DMitigation
Topics
#Risk Response Strategies#Risk Acceptance#Threat Responses
Community Discussion
No community discussion yet for this question.