nerdexam
PMI

PMI-RMP · Question #143

You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the…

The correct answer is C. Risk register. The risk register is the central document used to record all identified risks, their proposed responses, risk owners, and current status throughout the project.

Risk Monitoring and Reporting

Question

You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?

Options

  • AStakeholder management strategy
  • BRisk management plan
  • CRisk register
  • DLessons learned documentation

How the community answered

(57 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    88% (50)
  • D
    7% (4)

Why each option

The risk register is the central document used to record all identified risks, their proposed responses, risk owners, and current status throughout the project.

AStakeholder management strategy

The stakeholder management strategy documents how stakeholders will be engaged and communicated with, not the identification and status of project risk events.

BRisk management plan

The risk management plan describes the processes, roles, tools, and methodology to be used for risk management, but does not contain the individual risk events or their specific responses.

CRisk registerCorrect

The risk register is the living document that captures all identified risks along with their descriptions, probability, impact ratings, proposed responses, risk owners, and current status. It is continuously updated as risks are identified, analyzed, and as responses are planned and implemented. All risk-related information - including agreed responses - is consolidated in the risk register for tracking and reference.

DLessons learned documentation

Lessons learned documentation captures knowledge for future projects after events have occurred and is not a real-time tracking document for active risk responses and status.

Concept tested: Risk register as repository for risk responses and status

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Register#Risk Responses#Risk Documentation#Risk Status

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice