nerdexam
PMI

PMI-RMP · Question #118

Harry works as a project manager for BlueWell Inc. He is determining how to conduct the risk management activities for a project. According to the PMBOK, there are six inputs to the plan risk manageme

The correct answer is B. Risk management plan. The Risk Management Plan is the primary OUTPUT of the Plan Risk Management process - it cannot also be an input to the same process. You cannot plan risk management using a risk management plan that doesn't exist yet. The actual inputs to Plan Risk Management (per PMBOK) include:

Risk Strategy and Planning

Question

Harry works as a project manager for BlueWell Inc. He is determining how to conduct the risk management activities for a project. According to the PMBOK, there are six inputs to the plan risk management process. Which one of the following is NOT an input to this process?

Options

  • AProject scope statement
  • BRisk management plan
  • CSchedule management plan
  • DCost management plan

How the community answered

(21 responses)
  • B
    90% (19)
  • C
    5% (1)
  • D
    5% (1)

Explanation

The Risk Management Plan is the primary OUTPUT of the Plan Risk Management process - it cannot also be an input to the same process. You cannot plan risk management using a risk management plan that doesn't exist yet. The actual inputs to Plan Risk Management (per PMBOK) include: the Project Management Plan (which contains the scope, schedule, and cost management plans among others), the Project Charter, Stakeholder Register, Enterprise Environmental Factors, and Organizational Process Assets. The project scope statement, schedule management plan, and cost management plan are all valid inputs because they provide context for how risks should be managed.

Topics

#Plan Risk Management#Process Inputs#PMBOK Guide#Risk Planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice