PMI-RMP · Question #118
Harry works as a project manager for BlueWell Inc. He is determining how to conduct the risk management activities for a project. According to the PMBOK, there are six inputs to the plan risk manageme
The correct answer is B. Risk management plan. The Risk Management Plan is the primary OUTPUT of the Plan Risk Management process - it cannot also be an input to the same process. You cannot plan risk management using a risk management plan that doesn't exist yet. The actual inputs to Plan Risk Management (per PMBOK) include:
Question
Harry works as a project manager for BlueWell Inc. He is determining how to conduct the risk management activities for a project. According to the PMBOK, there are six inputs to the plan risk management process. Which one of the following is NOT an input to this process?
Options
- AProject scope statement
- BRisk management plan
- CSchedule management plan
- DCost management plan
How the community answered
(21 responses)- B90% (19)
- C5% (1)
- D5% (1)
Explanation
The Risk Management Plan is the primary OUTPUT of the Plan Risk Management process - it cannot also be an input to the same process. You cannot plan risk management using a risk management plan that doesn't exist yet. The actual inputs to Plan Risk Management (per PMBOK) include: the Project Management Plan (which contains the scope, schedule, and cost management plans among others), the Project Charter, Stakeholder Register, Enterprise Environmental Factors, and Organizational Process Assets. The project scope statement, schedule management plan, and cost management plan are all valid inputs because they provide context for how risks should be managed.
Topics
Community Discussion
No community discussion yet for this question.