nerdexam
PMIPMI

PMI-RMP · Question #117

PMI-RMP Question #117: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #117. The question stem and answer options stay visible for context.

Risk Monitoring and Reporting

Question

You are the project manager of the NHQ project for your company. Management has told you that you must implement an agreed upon contingency response if the Cost Performance Index in your project is less than 0.90. Consider that your project has a budget at completion of $250,000 and is 60 percent complete. You are scheduled to be however, 75 percent complete, and you have spent $165,000 to date. What is the Cost Performance Index for this project to determine if the contingency response should happen?

Options

  • A-$37,500
  • B0.91
  • C0.88
  • D0.80

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Management#Cost Performance Index#Risk Monitoring#Risk Response Triggers
Full PMI-RMP PracticeBrowse All PMI-RMP Questions