nerdexam
PMIPMI

PMI-RMP · Question #150

PMI-RMP Question #150: Real Exam Question with Answer & Explanation

The correct answer is C: Ishikawa diagrams. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

You work as a project manager for BlueWell Inc. You have to communicate the causes of risk events to the stakeholders. Which risk diagramming technique you will use to communicate the causes of risk events to project stakeholders?

Options

  • AProject network diagrams
  • BProcess flow charts
  • CIshikawa diagrams
  • DInfluence diagrams

Topics

#Risk communication#Ishikawa diagram#Cause-and-effect analysis#Risk reporting

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions