Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which one of the following will NOT help Wendy to perform this project management activity?
The correct answer is D. Stakeholder register. The inputs to the Qualitative Risk Analysis process are the Risk Register, Risk Management Plan, Project Scope Statement, and Organizational Process Assets. The Stakeholder Register is NOT an input to qualitative risk analysis - it is used in processes like stakeholder…
Question
Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which one of the following will NOT help Wendy to perform this project management activity?
Options
- AProject scope statement
- BRisk management plan
- CRisk register
- DStakeholder register
How the community answered
(38 responses)- A5% (2)
- B3% (1)
- C11% (4)
- D82% (31)
Explanation
The inputs to the Qualitative Risk Analysis process are the Risk Register, Risk Management Plan, Project Scope Statement, and Organizational Process Assets. The Stakeholder Register is NOT an input to qualitative risk analysis - it is used in processes like stakeholder management and communications planning. The project scope statement helps identify technical complexity, the risk management plan provides methodology and thresholds, and the risk register contains the list of identified risks to be analyzed. Since the stakeholder register does not contribute to assessing probability or impact of risks, it is the correct 'NOT helpful' answer.