PMIPMI
PMI-RMP · Question #152
PMI-RMP Question #152: Real Exam Question with Answer & Explanation
The correct answer is B: Sensitivity analysis. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
Frances is the project manager of a project in her organization. This project has a budget of $567,000 and is schedule to last for three years. Frances wants to examine the risk events to determine which risk events have the most potential impact on the project. Which modeling technique can help Frances to accomplish this goal?
Options
- AExpected monetary value
- BSensitivity analysis
- CQuantitative risk analysis
- DModeling and simulation
Topics
#Quantitative Risk Analysis#Sensitivity Analysis#Risk Impact Assessment#Risk Prioritization
Community Discussion
No community discussion yet for this question.