nerdexam
PMIPMI

PMI-RMP · Question #152

PMI-RMP Question #152: Real Exam Question with Answer & Explanation

The correct answer is B: Sensitivity analysis. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

Frances is the project manager of a project in her organization. This project has a budget of $567,000 and is schedule to last for three years. Frances wants to examine the risk events to determine which risk events have the most potential impact on the project. Which modeling technique can help Frances to accomplish this goal?

Options

  • AExpected monetary value
  • BSensitivity analysis
  • CQuantitative risk analysis
  • DModeling and simulation

Topics

#Quantitative Risk Analysis#Sensitivity Analysis#Risk Impact Assessment#Risk Prioritization

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions