The correct answer is A: Network diagram analysis of critical path activities. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You are the project manager for BlueWell Inc. You are reviewing the risk register for your project. The risk register provides much information to you, the project manager and to the project team during the risk response planning. All of the following are included in the risk register except for which item?

Options

  • ANetwork diagram analysis of critical path activities
  • BSymptoms and warning signs of risks
  • CList of potential risk responses
  • DTrends in qualitative risk analysis results

Topics

#Risk Register Content#Risk Information Management#Project Risk Planning