PMI-RMP · Question #153
You are the project manager for BlueWell Inc. You are reviewing the risk register for your project. The risk register provides much information to you, the project manager and to the project team…
The correct answer is A. Network diagram analysis of critical path activities. A Network Diagram Analysis of critical path activities is a schedule management tool - it belongs to the schedule network analysis process, not the risk register. The risk register is a document that contains identified risks, their descriptions, categories, root causes…
Question
You are the project manager for BlueWell Inc. You are reviewing the risk register for your project. The risk register provides much information to you, the project manager and to the project team during the risk response planning. All of the following are included in the risk register except for which item?
Options
- ANetwork diagram analysis of critical path activities
- BSymptoms and warning signs of risks
- CList of potential risk responses
- DTrends in qualitative risk analysis results
How the community answered
(55 responses)- A95% (52)
- C2% (1)
- D4% (2)
Explanation
A Network Diagram Analysis of critical path activities is a schedule management tool - it belongs to the schedule network analysis process, not the risk register. The risk register is a document that contains identified risks, their descriptions, categories, root causes, symptoms and warning signs, probability and impact ratings, risk owners, planned risk responses, and trends from qualitative analysis. It does not include network diagram outputs such as critical path calculations, which are part of schedule management artifacts.