You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the…

The correct answer is A. Stakeholder register. The Stakeholder Register is NOT an input to the Qualitative Risk Analysis process. The standard inputs are: the Risk Register (list of identified risks), the Risk Management Plan (defines roles, methodology, probability and impact scales), the Project Scope Statement (describes…

Risk Process Facilitation

Question

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?

Options

  • AStakeholder register
  • BProject scope statement
  • CRisk management plan
  • DRisk register

How the community answered

(47 responses)
  • A
    87% (41)
  • B
    4% (2)
  • C
    2% (1)
  • D
    6% (3)

Explanation

The Stakeholder Register is NOT an input to the Qualitative Risk Analysis process. The standard inputs are: the Risk Register (list of identified risks), the Risk Management Plan (defines roles, methodology, probability and impact scales), the Project Scope Statement (describes technical complexity and project context), and Organizational Process Assets (historical data, lessons learned). The stakeholder register is primarily used in stakeholder engagement and communications processes, not in assessing the probability and impact of individual risks.

Topics

#Qualitative Risk Analysis#Process Inputs#Risk Management Process#Project Documents