nerdexam
PMIPMI

PMI-RMP · Question #154

PMI-RMP Question #154: Real Exam Question with Answer & Explanation

The correct answer is A: Stakeholder register. See the full explanation below for the reasoning.

Risk Process Facilitation

Question

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?

Options

  • AStakeholder register
  • BProject scope statement
  • CRisk management plan
  • DRisk register

Topics

#Qualitative Risk Analysis#Process Inputs#Risk Management Process#Project Documents

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions