PMI-RMP · Question #155
Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?
The correct answer is C. Integrated change control. Integrated Change Control is the process that reviews all change requests, approves or rejects them, manages changes to deliverables, project documents, and the project management plan. As part of this process, every proposed change is evaluated for its impact - including risk…
Question
Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?
Options
- ARisk monitoring and control
- BScope change control
- CIntegrated change control
- DConfiguration management
How the community answered
(47 responses)- A2% (1)
- B4% (2)
- C83% (39)
- D11% (5)
Explanation
Integrated Change Control is the process that reviews all change requests, approves or rejects them, manages changes to deliverables, project documents, and the project management plan. As part of this process, every proposed change is evaluated for its impact - including risk impact - before it is approved. Scope Change Control only addresses scope-related changes, Risk Monitoring and Control tracks identified risks but does not govern change requests, and Configuration Management deals with product or system baselines. Integrated Change Control is the holistic gate through which all changes must pass, making it responsible for risk assessment of new change requests.