PMI-RMP Question #155: Real Exam Question with Answer & Explanation

The correct answer is C: Integrated change control. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?

Options

  • ARisk monitoring and control
  • BScope change control
  • CIntegrated change control
  • DConfiguration management