PMIPMI
PMI-RMP · Question #149
PMI-RMP Question #149: Real Exam Question with Answer & Explanation
The correct answer is B: Each agreed-to and funded risk response should have a risk response owner. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
You are the project manager of the NHH Project for your company and you have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Now, you would like to assign risk owners to the events. Which risk events should have risk response owners?
Options
- AOnly the risks with a high risk rating
- BEach agreed-to and funded risk response should have a risk response owner
- CEach risk that has a risk response should have a risk response owner
- DOnly the risk events that are considered a negative risk event with a high risk rating
Topics
#Risk response ownership#Risk response implementation#Accountability#Roles and responsibilities
Community Discussion
No community discussion yet for this question.