nerdexam
PMIPMI

PMI-RMP · Question #135

PMI-RMP Question #135: Real Exam Question with Answer & Explanation

The correct answer is A: Risk register. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?

Options

  • ARisk register
  • BRisk log
  • CRisk management plan
  • DProject management plan

Topics

#Risk Register#Risk Response Planning#Mitigation#Project Documents

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions