Risk Monitoring and Reporting

Question

You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declined change request be documented and stored?

Options

  • AChange request log
  • BLessons learned
  • CProject archives
  • DProject document updates

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Change Request Log#Project Documentation#Decision Documentation