PMI-RMP · Question #137
You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only output of the…
The correct answer is B. Risk register updates. The Perform Quantitative Risk Analysis process produces exactly one output: risk register updates, which incorporate the numerical analysis results.
Question
You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only output of the quantitative risk analysis process?
Options
- AProbability of reaching project objectives
- BRisk register updates
- CRisk response
- DRisk contingency reserve
How the community answered
(31 responses)- B94% (29)
- C3% (1)
- D3% (1)
Why each option
The Perform Quantitative Risk Analysis process produces exactly one output: risk register updates, which incorporate the numerical analysis results.
Probability of reaching project objectives is a specific type of information contained within the risk register updates output - it is not a separate standalone output of the process.
PMBOK defines risk register updates as the sole output of Perform Quantitative Risk Analysis. These updates contain the results of probabilistic analysis including probability of achieving objectives, a prioritized list of quantified risks, probability distributions for cost and schedule outcomes, and recommended contingency reserves - all consolidated into the risk register.
Risk responses are developed during the Plan Risk Responses process, which follows quantitative risk analysis in the PMBOK process sequence and is a distinct process with its own outputs.
Risk contingency reserves are calculated values documented as part of the risk register updates - they are findings within that output, not a separate output in their own right.
Concept tested: Output of Perform Quantitative Risk Analysis process
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok