nerdexam
PMI

PMI-RMP · Question #145

You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this…

The correct answer is C. Organizational process assets. Organizational process assets are inputs to the quantitative risk analysis process, not tools or techniques - making it the correct answer for what does NOT belong in the tools and techniques category.

Perform Targeted Risk Analysis

Question

You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?

Options

  • AExpert judgment
  • BData gathering and representation techniques
  • COrganizational process assets
  • DQuantitative risk analysis and modeling techniques

How the community answered

(34 responses)
  • A
    3% (1)
  • C
    91% (31)
  • D
    6% (2)

Why each option

Organizational process assets are inputs to the quantitative risk analysis process, not tools or techniques - making it the correct answer for what does NOT belong in the tools and techniques category.

AExpert judgment

Expert judgment is a legitimate tool and technique for quantitative risk analysis, used to assess probability distributions and validate analytical results when data is limited.

BData gathering and representation techniques

Data gathering and representation techniques, such as interviewing and probability distribution selection, are core tools used within the quantitative risk analysis process.

COrganizational process assetsCorrect

Organizational process assets such as historical project data, risk databases, and lessons learned from previous projects serve as inputs that feed into the quantitative risk analysis process, providing the raw information needed to conduct the analysis. They are not tools or techniques applied during the process itself, which is why this is the correct answer. The PMBOK Guide clearly distinguishes between process inputs, tools and techniques, and outputs.

DQuantitative risk analysis and modeling techniques

Quantitative risk analysis and modeling techniques - including Monte Carlo simulation and decision tree analysis - are the primary tools used to numerically assess overall project risk.

Concept tested: Inputs vs. tools and techniques in quantitative risk analysis

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Quantitative Risk Analysis#Tools and Techniques#Organizational Process Assets

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice