PMI-RMP · Question #131
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying…
The correct answer is D. Procurement management plan. This question tests knowledge of the eleven inputs to the Identify Risks process as defined in PMBOK. The procurement management plan is not among those inputs.
Question
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process?
Options
- AQuality management plan
- BCost management plan
- CStakeholder register
- DProcurement management plan
How the community answered
(22 responses)- A5% (1)
- C5% (1)
- D91% (20)
Why each option
This question tests knowledge of the eleven inputs to the Identify Risks process as defined in PMBOK. The procurement management plan is not among those inputs.
The quality management plan is one of the eleven inputs to Identify Risks because quality requirements and standards can directly introduce or affect project risk events.
The cost management plan is one of the eleven inputs to Identify Risks because cost thresholds, reserves, and constraints can generate or constrain risk responses.
The stakeholder register is one of the eleven inputs to Identify Risks because stakeholders contribute risk identification expertise and their tolerances shape risk evaluation.
According to PMBOK, the Identify Risks process has eleven inputs including the risk management plan, cost management plan, schedule management plan, quality management plan, human resource management plan, scope baseline, activity cost/duration estimates, stakeholder register, enterprise environmental factors, and organizational process assets. The procurement management plan is not a distinct input to this process - procurement documents may be referenced indirectly, but the procurement management plan itself is excluded.
Concept tested: Inputs to the Identify Risks process
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.