PMIPMI
PMI-RMP · Question #130
PMI-RMP Question #130: Real Exam Question with Answer & Explanation
The correct answer is A: Four. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative risk event in the project?
Options
- AFour
- BOne
- CThree
- DSeven
Topics
#Risk response planning#Negative risk responses#Threat strategies
Community Discussion
No community discussion yet for this question.