PMIPMI
PMI-RMP · Question #129
PMI-RMP Question #129: Real Exam Question with Answer & Explanation
The correct answer is A: It determines which risk events have the most potential impact on the project.. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
Joyce is the project manager for her company. Joyce and her project team are working through the quantitative analysis for certain risk events within her project. According to the enterprise environmental factors the project manager is to perform sensitivity analysis on any risk with an impact greater than $5,000 in the project. What is the sensitivity analysis?
Options
- AIt determines which risk events have the most potential impact on the project.
- BIt uses round of anonymous surveys to predict which events are most likely to happen.
- CIt uses rounds of anonymous surveys to predict probability and impact.
- DIt determines possible combinations of risk events to predict overall project success, failure, or probability of
Topics
#Sensitivity Analysis#Quantitative Risk Analysis#Risk Analysis Techniques
Community Discussion
No community discussion yet for this question.