PMIPMI
PMI-RMP · Question #114
PMI-RMP Question #114: Real Exam Question with Answer & Explanation
The correct answer is C: Risk transference. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?
Options
- ARisk acceptance
- BRisk avoidance
- CRisk transference
- DRisk mitigation
Topics
#Risk response planning#Risk transference#Threat response#Risk management strategies
Community Discussion
No community discussion yet for this question.