nerdexam
PMIPMI

PMI-RMP · Question #114

PMI-RMP Question #114: Real Exam Question with Answer & Explanation

The correct answer is C: Risk transference. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?

Options

  • ARisk acceptance
  • BRisk avoidance
  • CRisk transference
  • DRisk mitigation

Topics

#Risk response planning#Risk transference#Threat response#Risk management strategies

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions