PMIPMI
PMI-RMP · Question #115
PMI-RMP Question #115: Real Exam Question with Answer & Explanation
The correct answer is C: Recurrent projects. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Which types of project tends to have more well-understood risks?
Options
- AOperational work projects
- BFirst-of-its kind technology projects
- CRecurrent projects
- DState-of-art technology projects
Topics
#Project types#Risk characteristics#Recurrent projects#Risk understanding
Community Discussion
No community discussion yet for this question.