nerdexam
PMIPMI

PMI-RMP · Question #115

PMI-RMP Question #115: Real Exam Question with Answer & Explanation

The correct answer is C: Recurrent projects. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Which types of project tends to have more well-understood risks?

Options

  • AOperational work projects
  • BFirst-of-its kind technology projects
  • CRecurrent projects
  • DState-of-art technology projects

Topics

#Project types#Risk characteristics#Recurrent projects#Risk understanding

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions