nerdexam
PMIPMI

PMI-RMP · Question #133

PMI-RMP Question #133: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #133. The question stem and answer options stay visible for context.

Risk Monitoring and Reporting

Question

As a part of monitoring and controlling the project, the project manager should update the risk register. The project manager should update the risk register with information on risk reassessment, risk audits, and periodic risk reviews. What other information should the project manager update the risk register with?

Options

  • AActual costs and schedule delays of risk events.
  • BActual outcomes of risk management duties by the project team.
  • CActual cost of risk events.
  • DActual outcomes of the project's risks and of the risk responses.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Register#Monitor Risks#Risk Response Outcomes#Risk Event Outcomes
Full PMI-RMP PracticeBrowse All PMI-RMP Questions