nerdexam
PMI

PMI-RMP · Question #127

You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at…

The correct answer is D. 0.93. The Cost Performance Index (CPI) measures cost efficiency by dividing earned value by actual cost. With a BAC of $945,000 at 45% complete and actual spend of $455,897, the CPI calculates to approximately 0.93.

Risk Monitoring and Reporting

Question

You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

Options

  • A1.06
  • B0.92
  • C-$30,647
  • D0.93

How the community answered

(48 responses)
  • A
    13% (6)
  • B
    6% (3)
  • C
    4% (2)
  • D
    77% (37)

Why each option

The Cost Performance Index (CPI) measures cost efficiency by dividing earned value by actual cost. With a BAC of $945,000 at 45% complete and actual spend of $455,897, the CPI calculates to approximately 0.93.

A1.06

A CPI of 1.06 would indicate the project is performing under budget, which contradicts the data showing actual costs of $455,897 exceeding the earned value of $425,250.

B0.92

0.92 is slightly lower than the accurately calculated result of approximately 0.9327 and does not correctly reflect the division of earned value by actual cost.

C-$30,647

Negative $30,647 represents the cost variance (EV minus AC = $425,250 - $455,897), which is a dollar-denominated metric, not the dimensionless CPI ratio.

D0.93Correct

CPI = EV / AC, where EV = 45% x $945,000 = $425,250 and AC = $455,897. Dividing $425,250 by $455,897 yields approximately 0.9327, which rounds to 0.93 and confirms the contingency response threshold has been triggered since the CPI is not greater than 0.93.

Concept tested: Earned value management - Cost Performance Index calculation

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Cost Performance Index (CPI)#Earned Value Management (EVM)#Performance Measurement#Risk Triggers

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice