nerdexam
PMIPMI

PMI-RMP · Question #127

PMI-RMP Question #127: Real Exam Question with Answer & Explanation

The correct answer is D: 0.93. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

Options

  • A1.06
  • B0.92
  • C-$30,647
  • D0.93

Topics

#Cost Performance Index (CPI)#Earned Value Management (EVM)#Performance Measurement#Risk Triggers

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions