PMIPMI
PMI-RMP · Question #127
PMI-RMP Question #127: Real Exam Question with Answer & Explanation
The correct answer is D: 0.93. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?
Options
- A1.06
- B0.92
- C-$30,647
- D0.93
Topics
#Cost Performance Index (CPI)#Earned Value Management (EVM)#Performance Measurement#Risk Triggers
Community Discussion
No community discussion yet for this question.