PMI-RMP · Question #109

You are the project manager of the NHQ Project for your company. You are discussing some of the project issues that need to be resolved in the project. You and the project stakeholders come to an…

The correct answer is C. Issue log. The issue log (also called the issue register) is the project document specifically designed to track and document project issues, their status, assigned owners, and resolution details. When project issues are identified and agreements are reached on how to resolve them, those…

Risk Monitoring and Reporting

Question

You are the project manager of the NHQ Project for your company. You are discussing some of the project issues that need to be resolved in the project. You and the project stakeholders come to an agreement about the risk issues and how they will be resolved. Where should you document this information for issue resolution?

Options

  • AProject management plan for execution
  • BLessons learned documentation
  • CIssue log
  • DRisk response plan

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    93% (26)

Explanation

The issue log (also called the issue register) is the project document specifically designed to track and document project issues, their status, assigned owners, and resolution details. When project issues are identified and agreements are reached on how to resolve them, those details belong in the issue log. The project management plan governs execution; lessons learned captures knowledge after resolution; the risk response plan addresses future risk events before they become issues.

Topics

#Issue management#Issue log#Documentation#Risk resolution