PMI-RMP · Question #109
PMI-RMP Question #109: Real Exam Question with Answer & Explanation
The correct answer is C: Issue log. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
You are the project manager of the NHQ Project for your company. You are discussing some of the project issues that need to be resolved in the project. You and the project stakeholders come to an agreement about the risk issues and how they will be resolved. Where should you document this information for issue resolution?
Options
- AProject management plan for execution
- BLessons learned documentation
- CIssue log
- DRisk response plan
Topics
#Issue management#Issue log#Documentation#Risk resolution