- Question #318Tools and documentation
A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet t...
Project trackingDeliverable managementProject toolsBacklog - Question #319Project Management Concepts
A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. W...
Lessons learnedKnowledge managementProject documentationPost-project review - Question #320Project Management Concepts
During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following sh...
Risk ManagementSchedule ManagementContingency PlanningCritical Path - Question #321Tools and documentation
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for...
Project initiationBusiness caseProject documentationProject justification - Question #322Basics of IT and governance
Which of the following would be the most helpful in providing customers with an application accessible via a web browser?
Cloud ComputingSaaSService ModelsApplication Delivery - Question #323Project Management Concepts
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasiz...
Procurement managementVendor selectionOutsourcingProject planning - Question #324Project Management Concepts
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
Change managementChange Control Board (CCB)Project manager responsibilitiesProject constraints - Question #325Tools and documentation
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason the...
RACI matrixRoles and responsibilitiesTeam conflictProject execution - Question #326Project Management Concepts
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and...
Agile PlanningCadenceProject SchedulingConsistent Flow - Question #327Basics of IT and governance
Which of the following statements best represents a network issue?
Network troubleshootingIncident identificationIT issuesService disruption - Question #328Project Life Cycle Phases
A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?
Project InitiationBusiness NeedsProject DefinitionProject Start-up - Question #329Project Management Concepts
A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay...
Issue ManagementProject DocumentationProject ControlProblem Solving - Question #330Project Management Concepts
During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best metho...
Project methodologiesAgile ScrumIterative developmentStakeholder communication - Question #331Basics of IT and governance
A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the pr...
Change ManagementProject GovernanceProcess ComplianceProject Manager Responsibilities - Question #332Project Management Concepts
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the s...
Project CharterSuccess CriteriaProject SponsorProject Manager Roles - Question #333Project Management Concepts
A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a...
Stakeholder managementConflict resolutionNegotiationCompromise - Question #334Project Management Concepts
A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?
SLAService Level AgreementClient agreementResolution time - Question #335Project Life Cycle Phases
Which of the following is the most important activity for the project manager during the closure of a project?
Project ClosureProject Manager ResponsibilitiesProject Sign-offProject Life Cycle - Question #336Project Management Concepts
Which of the following best describes a benefit of the CI/CD process?
CI/CDSoftware DeliveryAgile MethodologiesProcess Improvement - Question #337Project Management Concepts
During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the followi...
Project Quality ManagementCorrelation AnalysisProject PerformanceData Analysis - Question #338Tools and documentation
A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?
Pareto principle80/20 ruleQuality control toolsProblem-solving diagrams - Question #339Tools and documentation
Which of the following should a project manager consult when deciding how to send updates regarding deliverables?
Communication planProject communicationStakeholder managementProject documentation - Question #340Tools and documentation
Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software projec...
Cloud computingPaaSSoftware developmentCloud service models - Question #341Project Management Concepts
A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor d...
Enterprise Resource Planning (ERP)Business integrationProject requirementsSystem types - Question #342Project Management Concepts
Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?
Contract typesScope uncertaintyRisk managementProject procurement - Question #343Project Management Concepts
A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the projec...
Agile methodologyTeam communicationAgile principles - Question #344Tools and documentation
A project manager provided details regarding the completion of the following tasks: - Vendor selection took less time than planned. - Equipment procurement took less time than esti...
Gantt chartSchedule managementProgress trackingProject updates - Question #345Project Management Concepts
A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the ex...
Conflict ResolutionDecision MakingProject Management TechniquesForcing - Question #346Project Management Concepts
A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?
Decision treeVendor analysisRisk managementCost analysis - Question #347Tools and documentation
A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?
Defect managementProject documentationQuality managementProject logs - Question #348Project Management Concepts
Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?
Risk ManagementContingency PlanningRisk ResponseIncident Management - Question #349Tools and documentation
A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partne...
ProcurementVendor SelectionProposalsBusiness Partnerships - Question #350Project Management Concepts
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?
Rollback planSoftware deploymentSmoke testingContingency planning - Question #351Basics of IT and governance
When assigning access, classifying information based on sensitivity is referred to as:
Information classificationData securityAccess controlSensitivity - Question #352Tools and documentation
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Whi...
Risk ManagementRisk LogProject DocumentationResource Management - Question #353Project Management Concepts
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project...
Project SchedulingGo-live PlanningDowntime ManagementOperational Impact - Question #354Project Management Concepts
Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decide...
Risk ManagementRisk Response StrategiesRisk TransferProject Execution - Question #355Project Management Concepts
Which of the following is a characteristic that defines a project?
Project definitionProject characteristicsTemporary nature - Question #356Project Life Cycle Phases
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes...
Project ClosureVendor ManagementContract ManagementProject Life Cycle - Question #357Project Management Concepts
A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the dev...
Risk ManagementImpact AnalysisProject BaselinesChange Management - Question #358Tools and documentation
During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager us...
Project schedulingProject dependenciesPrecedence Diagramming MethodProject initiation - Question #359Project Life Cycle Phases
A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?
Communication planningAccess managementProject life cycle phasesPlanning phase - Question #360Basics of IT and governance
A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?
Cloud computingIaaSDevelopment environmentCloud service models - Question #361Project Management Concepts
Which of the following is a quantitative key performance indicator?
Key Performance Indicators (KPIs)Quantitative metricsProject performanceMeasurement - Question #362Tools and documentation
Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?
RACI matrixCommunication planningStakeholder managementProject artifacts - Question #363Tools and documentation
During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the follo...
Risk ManagementProject DocumentationRisk RegisterCommunication Tools - Question #364Project Management Concepts
Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?
Agile methodologiesScrum eventsSprint reviewBacklog management - Question #365Project Management Concepts
Which of the following best describes the meaning of timeboxing in the context of a project kickoff meeting?
TimeboxingMeeting managementProject meetingsProject kickoff - Question #366Project Management Concepts
A project manager is monitoring the performance of the development team and creates the following view: - Planned Task Completion - Actual Task Completion Which of the following de...
Project monitoringSchedule managementPerformance measurementProject status - Question #367Project Management Concepts
A project team member has been interacting on personal social media instead of performing assigned tasks. This behavior is explicitly forbidden in the team charter. Which of the fo...
Team ManagementTeam Charter EnforcementPerformance ManagementPM Communication