A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as…

The correct answer is B. The majority of the team can only meet on a weekly basis. In Agile, frequent and consistent communication is critical for collaboration, alignment, and iterative progress. If the majority of the team can only meet once a week, it hinders daily standups, quick feedback loops, and timely adjustments, making this a significant concern.

Project Management Concepts

Question

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

Options

  • AEach feature will have a different owner.
  • BThe majority of the team can only meet on a weekly basis.
  • CThe stakeholders have provided a specific deadline to meet.
  • DEach feature has a specific budget allocation.

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    74% (14)
  • C
    16% (3)
  • D
    5% (1)

Explanation

In Agile, frequent and consistent communication is critical for collaboration, alignment, and iterative progress. If the majority of the team can only meet once a week, it hinders daily standups, quick feedback loops, and timely adjustments, making this a significant concern.

Topics