PK0-005 · Question #343
PK0-005 Question #343: Real Exam Question with Answer & Explanation
The correct answer is B: The majority of the team can only meet on a weekly basis.. In Agile, frequent and consistent communication is critical for collaboration, alignment, and iterative progress. If the majority of the team can only meet once a week, it hinders daily standups, quick feedback loops, and timely adjustments, making this a significant concern.
Question
A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?
Options
- AEach feature will have a different owner.
- BThe majority of the team can only meet on a weekly basis.
- CThe stakeholders have provided a specific deadline to meet.
- DEach feature has a specific budget allocation.
Explanation
In Agile, frequent and consistent communication is critical for collaboration, alignment, and iterative progress. If the majority of the team can only meet once a week, it hinders daily standups, quick feedback loops, and timely adjustments, making this a significant concern.