A project is behind schedule. Which of the following actions should a project manager take to meet the stated objectives and put the project back on schedule?
The correct answer is B. Add resources to work on project tasks. Adding resources to critical tasks is a schedule compression technique used to accelerate work and recover lost time, helping bring the project back on schedule while still meeting the stated
Project Management Concepts
Question
A project is behind schedule. Which of the following actions should a project manager take to meet the stated objectives and put the project back on schedule?
Options
- ALeave the project.
- BAdd resources to work on project tasks.
- CRedefine the project scope.
- DRemove deliverables from the project.
How the community answered
(37 responses)- A3% (1)
- B92% (34)
- C5% (2)
Explanation
Adding resources to critical tasks is a schedule compression technique used to accelerate work and recover lost time, helping bring the project back on schedule while still meeting the stated
Topics
#Schedule management#Corrective actions#Resource management#Schedule compression