nerdexam
CompTIA

PK0-005 · Question #620

A project is behind schedule. Which of the following actions should a project manager take to meet the stated objectives and put the project back on schedule?

The correct answer is B. Add resources to work on project tasks. Adding resources to critical tasks is a schedule compression technique used to accelerate work and recover lost time, helping bring the project back on schedule while still meeting the stated

Project Management Concepts

Question

A project is behind schedule. Which of the following actions should a project manager take to meet the stated objectives and put the project back on schedule?

Options

  • ALeave the project.
  • BAdd resources to work on project tasks.
  • CRedefine the project scope.
  • DRemove deliverables from the project.

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    92% (34)
  • C
    5% (2)

Explanation

Adding resources to critical tasks is a schedule compression technique used to accelerate work and recover lost time, helping bring the project back on schedule while still meeting the stated

Topics

#Schedule management#Corrective actions#Resource management#Schedule compression

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice