nerdexam
CompTIA

PK0-005 · Question #621

A team has updated a Gantt chart for an in-progress project. The project manager evaluates the performance of the project based on the following visualization: Which of the following can be inferred?

The correct answer is D. The project is over budget and behind schedule. The visualization shows that actual costs exceed planned values for completed work while progress is behind what was scheduled at the reporting period. This indicates negative cost and schedule performance, meaning the project is both over budget and behind schedule.

Project Management Concepts

Question

A team has updated a Gantt chart for an in-progress project. The project manager evaluates the performance of the project based on the following visualization:

Which of the following can be inferred?

Exhibit

PK0-005 question #621 exhibit

Options

  • AThe project will be completed on time.
  • BTask D must be reworked.
  • CTask В needs to be finished before task С starts.
  • DThe project is over budget and behind schedule.

How the community answered

(52 responses)
  • A
    4% (2)
  • B
    8% (4)
  • C
    13% (7)
  • D
    75% (39)

Explanation

The visualization shows that actual costs exceed planned values for completed work while progress is behind what was scheduled at the reporting period. This indicates negative cost and schedule performance, meaning the project is both over budget and behind schedule.

Topics

#Project performance#Gantt charts#Schedule management#Cost management

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice