PK0-005 · Question #323
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical…
The correct answer is B. Preliminary procurement. Preliminary procurement refers to the early stages of the procurement process, where the project manager or organization outlines the necessary skills, qualifications, and requirements for potential vendors. In this case, the car manufacturer is presenting the qualifications…
Question
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
Options
- AKey stakeholder identification
- BPreliminary procurement
- CSolution design determination
- DCritical factor enlistment
How the community answered
(42 responses)- A5% (2)
- B76% (32)
- C14% (6)
- D5% (2)
Explanation
Preliminary procurement refers to the early stages of the procurement process, where the project manager or organization outlines the necessary skills, qualifications, and requirements for potential vendors. In this case, the car manufacturer is presenting the qualifications and skills required for the vendors to develop a module of the data warehouse application, which fits the description of preliminary procurement. This is the stage where the organization defines what it needs from the vendors before formally requesting proposals or initiating contracts.