CompTIA
PK0-005 · Question #324
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
The correct answer is B. Escalate to the CCB. Escalating to the Change Control Board (CCB) is necessary when a change request impacts the project's timeline or budget. The CCB reviews and approves changes, ensuring that they align with project objectives.
Project Management Concepts
Question
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
Options
- AUpdate the WBS.
- BEscalate to the CCB.
- CAccept the change.
- DImplement the change.
How the community answered
(33 responses)- A18% (6)
- B70% (23)
- C9% (3)
- D3% (1)
Explanation
Escalating to the Change Control Board (CCB) is necessary when a change request impacts the project's timeline or budget. The CCB reviews and approves changes, ensuring that they align with project objectives.
Topics
#Change management#Change Control Board (CCB)#Project manager responsibilities#Project constraints
Community Discussion
No community discussion yet for this question.