Project Management Concepts
Question
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
Options
- AUpdate the WBS.
- BEscalate to the CCB.
- CAccept the change.
- DImplement the change.
Unlock PK0-005 to see the answer
You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change management#Change Control Board (CCB)#Project manager responsibilities#Project constraints