PK0-005 · Question #325
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
The correct answer is B. Information is missing from the RACI matrix. A RACI matrix clarifies roles and responsibilities for tasks, reducing confusion and disagreements among team members. Missing or incomplete information in the RACI matrix could lead to disputes, as it is a key tool for accountability in project management per CompTIA Project+.
Question
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
Options
- ASome work packages are missing from the WBS.
- BInformation is missing from the RACI matrix.
- CNew knowledge bases were introduced.
- DTeam touch points are missing.
How the community answered
(31 responses)- A10% (3)
- B84% (26)
- C3% (1)
- D3% (1)
Explanation
A RACI matrix clarifies roles and responsibilities for tasks, reducing confusion and disagreements among team members. Missing or incomplete information in the RACI matrix could lead to disputes, as it is a key tool for accountability in project management per CompTIA Project+.