PK0-005 · Question #530

PK0-005 Question #530: Real Exam Question with Answer & Explanation

The correct answer is A: Gantt chart. A Gantt chart visually displays the project schedule, showing phases, tasks, durations, and progress over time. It is ideal for keeping sponsors informed about the status of each phase and

Tools and documentation

Question

A project sponsor wants to be aware of the project's progress by phases and tasks. Which of the following tools will satisfy this request?

Options

  • AGantt chart
  • BNetwork diagram
  • CProject dashboard
  • DWork breakdown structure

Explanation

A Gantt chart visually displays the project schedule, showing phases, tasks, durations, and progress over time. It is ideal for keeping sponsors informed about the status of each phase and

Topics

#Gantt chart#Project progress tracking#Project management tools#Stakeholder communication