The correct answer is A: Gantt chart. A Gantt chart visually displays the project schedule, showing phases, tasks, durations, and progress over time. It is ideal for keeping sponsors informed about the status of each phase and
Tools and documentation
Question
A project sponsor wants to be aware of the project's progress by phases and tasks. Which of the following tools will satisfy this request?
Options
- AGantt chart
- BNetwork diagram
- CProject dashboard
- DWork breakdown structure
Explanation
A Gantt chart visually displays the project schedule, showing phases, tasks, durations, and progress over time. It is ideal for keeping sponsors informed about the status of each phase and
Topics
#Gantt chart#Project progress tracking#Project management tools#Stakeholder communication