PK0-005 · Question #54

PK0-005 Question #54: Real Exam Question with Answer & Explanation

The correct answer is C: Pareto chart. The Pareto chart is used to identify the most significant or critical problems or causes, so that resources can be allocated effectively to address them. It helps to prioritize the areas of improvement and focus on the problems or causes that have the greatest impact.

Tools and documentation

Question

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

Options

  • AIshikawa diagram
  • BScatter diagram
  • CPareto chart
  • DDecision tree

Explanation

The Pareto chart is used to identify the most significant or critical problems or causes, so that resources can be allocated effectively to address them. It helps to prioritize the areas of improvement and focus on the problems or causes that have the greatest impact.

Topics

#Quality Management Tools#Pareto Analysis#Problem Prioritization#Project Management Tools