PK0-005 · Question #53
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
The correct answer is D. Reconciling the budget. Evaluating the project is an activity that should be used in the closing phase of a project to support the project triple constraint. This involves reviewing the project plan, deliverables, and outcomes to ensure they meet the project objectives and requirements.
Question
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
Options
- AEvaluating the project
- BReleasing the resources
- CClosing the contracts
- DReconciling the budget
How the community answered
(39 responses)- A8% (3)
- B8% (3)
- C3% (1)
- D82% (32)
Explanation
Evaluating the project is an activity that should be used in the closing phase of a project to support the project triple constraint. This involves reviewing the project plan, deliverables, and outcomes to ensure they meet the project objectives and requirements.