As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

The correct answer is C. Seek baseline approval. Once the PM has defined tasks, durations, resources, and costs, the project plan elements (scope, schedule, and cost baselines) are effectively established. The logical next step is to seek formal approval of these baselines from stakeholders or sponsors. Approval sets the…

Project Life Cycle Phases

Question

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

Options

  • AUpdate the work breakdown structure.
  • BReview the backlog.
  • CSeek baseline approval.
  • DEstablish the resource pool.

How the community answered

(37 responses)
  • A
    14% (5)
  • B
    3% (1)
  • C
    78% (29)
  • D
    5% (2)

Explanation

Once the PM has defined tasks, durations, resources, and costs, the project plan elements (scope, schedule, and cost baselines) are effectively established. The logical next step is to seek formal approval of these baselines from stakeholders or sponsors. Approval sets the performance measurement baseline against which project progress will be tracked. The WBS should already be complete before tasks and durations are defined. The resource pool is established before assigning resources to tasks. The backlog is a concept from agile and would have been reviewed earlier in planning.

Topics

#Project planning#Project baselines#Project life cycle#Approval process