PK0-005 · Question #247
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager…
The correct answer is B. Release the project resources. When a project closes, the project manager is responsible for formally releasing project resources - this includes people, equipment, and financial accounts. Releasing resources means formally transitioning team members off the project so their time can be reallocated to other…
Question
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
Options
- ARemove the team member's access.
- BRelease the project resources.
- CCollect the stakeholders' feedback.
- DHave the closeout report approved.
How the community answered
(36 responses)- A3% (1)
- B89% (32)
- C6% (2)
- D3% (1)
Explanation
When a project closes, the project manager is responsible for formally releasing project resources - this includes people, equipment, and financial accounts. Releasing resources means formally transitioning team members off the project so their time can be reallocated to other work. Because the PM did not release the team member as a project resource, the system still associates them with the closed project, preventing them from logging time elsewhere. Removing access (A) is a separate activity related to systems/tools. Collecting stakeholder feedback (C) and getting the closeout report approved (D) are closure tasks but do not directly control resource time-charging; the root cause here is the failure to release the resource.