PK0-005 · Question #226

PK0-005 Question #226: Real Exam Question with Answer & Explanation

The correct answer is D: Review assumptions and constraints for input to the risk register.. During the planning phase, the team should review assumptions and constraints as part of the process of identifying potential risks. Assumptions and constraints can significantly impact the project, so understanding and documenting them is essential for creating an accurate risk

Project Life Cycle Phases

Question

A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?

Options

  • AIdentify and assess stakeholders.
  • BHold daily status meetings.
  • CRemove access and plan the project sign-off.
  • DReview assumptions and constraints for input to the risk register.

Explanation

During the planning phase, the team should review assumptions and constraints as part of the process of identifying potential risks. Assumptions and constraints can significantly impact the project, so understanding and documenting them is essential for creating an accurate risk register. This helps the team anticipate risks that might arise during execution and plan

Topics

#Project planning#Risk management#Assumptions and constraints#Project life cycle phases