A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

The correct answer is B. Identify business needs and product descriptions. The first step the project manager should take is to identify business needs and product descriptions. This is crucial for understanding the project's objectives and the specific requirements of the international supplier. Once these needs and descriptions are clear, the…

Project Life Cycle Phases

Question

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

Options

  • AIdentify project risks and plans to address them.
  • BIdentify business needs and product descriptions.
  • CCreate a work breakdown structure for the project.
  • DCreate a work schedule for the project team to follow.

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    88% (22)
  • D
    8% (2)

Explanation

The first step the project manager should take is to identify business needs and product descriptions. This is crucial for understanding the project's objectives and the specific requirements of the international supplier. Once these needs and descriptions are clear, the project manager can move on to more detailed planning, such as risk identification, scheduling, and creating a work breakdown structure (WBS). Establishing the business context and product scope sets the foundation for the entire project.

Topics

#Project Initiation#Business Needs#Project Definition#Project Start-up