PK0-005 · Question #470
The project manager must create a project charter. Which of the following should be included in the charter?
The correct answer is D. Stakeholder identification. The project charter is a high-level authorization document that outlines the purpose, objectives, and identifies key stakeholders. It does not contain detailed schedules, risk management plans, or resource allocation -- those come later in the planning process.
Question
The project manager must create a project charter. Which of the following should be included in the charter?
Options
- AProject schedule
- BResource allocation
- CRisk plan
- DStakeholder identification
How the community answered
(47 responses)- A4% (2)
- B2% (1)
- C6% (3)
- D87% (41)
Explanation
The project charter is a high-level authorization document that outlines the purpose, objectives, and identifies key stakeholders. It does not contain detailed schedules, risk management plans, or resource allocation -- those come later in the planning process.