The project manager must create a project charter. Which of the following should be included in the charter?

The correct answer is D. Stakeholder identification. The project charter is a high-level authorization document that outlines the purpose, objectives, and identifies key stakeholders. It does not contain detailed schedules, risk management plans, or resource allocation -- those come later in the planning process.

Project Life Cycle Phases

Question

The project manager must create a project charter. Which of the following should be included in the charter?

Options

  • AProject schedule
  • BResource allocation
  • CRisk plan
  • DStakeholder identification

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    6% (3)
  • D
    87% (41)

Explanation

The project charter is a high-level authorization document that outlines the purpose, objectives, and identifies key stakeholders. It does not contain detailed schedules, risk management plans, or resource allocation -- those come later in the planning process.