CompTIACompTIA
PK0-005 · Question #329
PK0-005 Question #329: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-005 to reveal the answer and full explanation for question #329. The question stem and answer options stay visible for context.
Project Management Concepts
Question
A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?
Options
- AConsult with the legal department.
- BUpdate the issue log.
- CStart a new RFP immediately.
- DPerform a PERT analysis.
Unlock PK0-005 to see the answer
You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Issue Management#Project Documentation#Project Control#Problem Solving