PK0-005 · Question #329
A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project…
The correct answer is B. Update the issue log. The Issue Log is where the project manager should first document any issues that arise during the project, including the vendor bankruptcy. The issue log helps track the problem, its impact on the project, and the actions taken to resolve it. This allows the project manager and…
Question
A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?
Options
- AConsult with the legal department.
- BUpdate the issue log.
- CStart a new RFP immediately.
- DPerform a PERT analysis.
How the community answered
(64 responses)- A6% (4)
- B75% (48)
- C3% (2)
- D16% (10)
Explanation
The Issue Log is where the project manager should first document any issues that arise during the project, including the vendor bankruptcy. The issue log helps track the problem, its impact on the project, and the actions taken to resolve it. This allows the project manager and team to keep stakeholders informed about the situation and manage the issue in a structured way.
Topics
Community Discussion
No community discussion yet for this question.